Experts say bringing floating bridge back would not solve issues

Bringing the Floating Bridge 5 (FB5) back would not solve the current issues seen on the crossing over the River Medina, experts have said.

The Isle of Wight Council has reviewed the Cowes to East Cowes crossing which has been plagued with issues since the new Floating Bridge 6 (FB6) was brought into service in 2017.

Computer modelling has been used by consultants 3S to create the environment of the River Medina and predict the outcome of design modifications, without the time and expenses of putting the fixes into place.

The review has ultimately found the FB6 cannot operate without the use of a push boat in strong tides — but neither could the former FB5.

Speaking at a meeting of the council’s corporate scrutiny committee yesterday (Tuesday), 3S said FB6 was working but it was failing to meet the targets set out in the business case like the average number of crossings required.

The average time it took FB6 to cross the river was 3 minutes and 30 seconds, a “snail’s pace” compared to FB5’s two-minute journeys, 3S said.

However, the answer is not to bring back FB5 as is commonly said, 3S revealed, as it would not comply with the chain depth required by the Cowes Harbour Master.

The chain depth requirement was introduced after FB5 was taken out of service.

They said any replacement vessel would have to be radically redesigned, with a new hull and superstructure, or a push boat may be necessary even into the future.

Cllr Clare Mosdell questioned whether other options, like a permanent road bridge, would be a better river crossing.

3S said work had been done in the past to see if there was a viable alternative including a tunnel, but it would have to start in Wootton and finish the other side of West Cowes.

They also said a bridge had been considered but it would be a serious impediment to tall river traffic.

The consultants said a floating bridge crossing was the most logical solution, however there was no fix for FB6 that would be worth spending money on.

3S also highlighted issues in the original contract specifications for FB6 which stipulated it should be made of steel and how long it should be, with the contractors facing financial penalties if it was not the specified length.

The scrutiny committee agreed the only feasible option was to now get a new floating bridge and to ‘get on with’ the process of procuring one.

Alternatives and next steps are being considered next month by the scrutiny committee and cabinet.